Hillcon HSCX700GLS - Vroom Funderingstechnieken
Img 07

Hillcon HSCX700GLS

The Hillcon HSCX700GLS pile driving rig was specially developed for the production of displacing screw piles with lengths of up to approx. 39 m, but can also be used for pre-fab concrete piles.

The leader is linked to the rig by means of two guides at the top and a sliding bed on the bottom. The leader can be set to various angles, can be adjusted and remains very stable. Of course, such settings depend on the dimensions and the weight of the pile and the plant and equipment with which these machines work.

Specifications, Hitachi HSCX700GLS

Weight class

In operation approx. 120 - 140 t.

Suitability for working with piles at an angle

Can be hydraulically set to various angles, tilting forward or backward.

Leader length

Max. approx. 43 m.

Maximum pile length

  • Cast in-situ screw piles, approx. 39 m.
  • Pre-fab concrete piles, approx. 32 m.