Hitachi KH150-3GLS

The Hitachi KH150-3GLS pile driving rig was specially developed for the production of relatively lightweight vibrated piles and pre-fab concrete piles with lengths of up to approx. 26 m.

The leader is linked to the rig by means of two guides at the top and a sliding bed on the bottom. The leader can be set to various angled positions. Of course, such settings depend on the dimensions and the weight of the pile and the plant and equipment with which these machines work.

Specifications, Hitachi KH150-3GLS

Weight class

In operation approx. 80 - 100 t.

Suitability for working with piles at an angle

Can be hydraulically adjusted smoothly, tilting forward or backward.

Leader length

Max. approx. 33 m.

Maximum pile length

Vibrated cast in-situ piles, approx. 26 m.

Pre-fab concrete piles, approx. 26m.