The Amsterdam Mosveldcomplex is being renovated. For this purpose, foundation piles are needed on a location that can only be accessed through a small alley so it is time to send one of our mini rigs in order to finish the job.
Default img 0666

15-m segment piles will be inserted to repair the foundation. A total of 30 piles will be inserted in 2 stages. Also steel segments have been delivered through the small alley and therefore, these segments are short and are connected to each other on-site resulting into a complete pile.