22 Molenbuurt homes

129 Palen11 Bergingsvloeren

HSB is continuing to work in Wormer. This time, we will apply the piles and the prefab shed floors for 22 new homes on Moriaanstraat. As this is an infill-location, we have opted for low-vibration DPA piles of which we will realize 129.

The 22 homes are part of 2 blocks. All homes in Molenbuurt will be built in one stage. Given the location in the centre of Wormer, we have decided about the ideal route for the delivery of our rig and other machinery before the start of the construction process.

DPA piles

After the DPA piles have been produced, they have to harden out for 5 days before we perform a continuity test (quality check). Subsequently, HSB Bouw will directly continue the realization of the foundation. Given the short construction period, we did not wait to perform the continuity test until all piles had been produced. Right after the first block was finished, those piles have been checked so that HSB could start the activities.

22 Molenbuurt homes
22 Molenbuurt homes
22 Molenbuurt homes
22 Molenbuurt homes
22 Molenbuurt homes
22 Molenbuurt homes
22 Molenbuurt homes
22 Molenbuurt homes

Can we help you with your project?

We are happy to answer your questions! Would you like to know more about our projects, products and/or services? Please contact Sandro Pronk

Sandro Pronk

Share project:

Realization
07-03-2016 to 23-03-2016
Location
Wormer
Client
WormerWonen / HSB Ontwikkeling
Contractor
HSB Bouw
Architect
W3
 
Fred Klaver
Project Manager