Company hall De Veken

898 piles2 rigs

Vroom is applying almost 900 heavy prefab foundation piles for a company hall. Underneath the floor area as well as underneath the construction, the piles will be applied by us at height. For the loading pit, the piles will be placed at several heights.

There is not much time for the execution process so therefore the project is being realized with two rigs working simultaneously. The job will be done within 2 weeks with contractor N.P. Bakker starting the activities for the foundation afterwards.

Company hall De Veken
Company hall De Veken
Company hall De Veken
Company hall De Veken
Company hall De Veken
Company hall De Veken

Can we help you with your project?

We are happy to answer your questions! Would you like to know more about our projects, products and/or services? Please contact Sandro Pronk

Sandro Pronk

Share project:

Realization
04-04-2016 to 18-04-2016
Location
Opmeer
Client
Hogherwoude
Contractor
NP Bakker
 
Dick Reijnders
Project Manager