Schipper Vloeren will take care of the floor for the building whereas the capacity will be taken care of by us. We will use VSD piles for this purpose. Per day, we are producing over 200 piles so that the execution process will take approximately three weeks. A total of over 21 km of VSD piles will be processed.
Company hall for Nobels Javo
2473 piles21 km pile
On the Bulb Trade Park site in Noordwijkerhout, the company hall for the Jano Holding will be realized in two state-of-the-art buildings on a central spot. Currently, they are situated on three different locations in Katwijk and Noordwijkerhout.