Production hall converted into data centre

3750 m2 of concrete floor 904 piles (AMS05)

At the end of the summer of 2020, we started converting an existing production hall on the Koolhovenlaan in Schiphol-Rijk to a data centre.

Having started with the conversion of a production hall into a data centre in late 2015 (AMS01), this was followed by AMS02, AMS03 and AMS04. It is now the turn of AMS05 for conversion and expansion. As the force exerted on the floor of the new data centre requires a greater load-bearing capacity than when it was in use as a production hall, we have extended the foundations using extra piles, coupled with a new concrete floor. The work involved in AMS05 was completed in October 2021.

The work was carried out by Winthrop Contracting and Engineering, an Irish contractor specialised in building data centres. Winthrop works with high-level safety culture, which means that a verifiable risk analysis must be conducted in advance of the work, there must be on-going safety monitoring and the managers of all contractors must conduct safety walk-arounds.

Varied work

The work involved the following activities:

  • Internal production of 341 grout-injected tube screw piles for a new steel structure
  • External production of 125 tube screw piles for generator racks
  • Production of 438 DPA piles, diameter 360 mm and length 13 metres, for the expansion of the data hall
  • Production of 140 in-situ 2 and 3 pile foundation blocks for generator racks
  • Production of 125 1 pile foundation blocks for generator racks
  • Production of 3,750 m2 of concrete flooring with edge beams and foundation blocks, for the expansion of the data hall
  • Associated earth works and creation of work platforms.
Production hall converted into data centre
Production hall converted into data centre
Production hall converted into data centre
Production hall converted into data centre
Production hall converted into data centre
Production hall converted into data centre
Production hall converted into data centre
Production hall converted into data centre
Production hall converted into data centre

Varied work

The work involved the following activities:

  • Internal production of 341 grout-injected tube screw piles for a new steel structure
  • External production of 125 tube screw piles for generator racks
  • Production of 438 DPA piles, diameter 360 mm and length 13 metres, for the expansion of the data hall
  • Production of 140 in-situ 2 and 3 pile foundation blocks for generator racks
  • Production of 125 1 pile foundation blocks for generator racks
  • Production of 3,750 m2 of concrete flooring with edge beams and foundation blocks, for the expansion of the data hall
  • Associated earth works and creation of work platforms.

Can we help you with your project?

We are happy to answer your questions! Would you like to know more about our projects, products and/or services? Please contact Sjakko Bikker

Sjakko Bikker

Share project:

Realization
06-07-2020 to 15-10-2021
Location
Schiphol-Rijk
Client
Winthrop Engineering & Contracting Ltd.
Contractor
Winthrop N.V.
Architect
EdgeConneX

Can we help you with your project?

We are happy to answer your questions! Would you like to know more about our projects, products and/or services? Please contact Sjakko Bikker

Sjakko Bikker

Share project:

To top