In the canal area on the border of Beersel and Sint-Pieter-Leeuw, 5 windmills are being placed. For the foundation of the mills, Vroom International Piling has applied the VGS piles. The production process of the piles takes place on-site, completely with a low vibration and a low sound level, and grout has been poured in-situ.

The 5 windmills are being placed each on their own dock. For this purpose, the rig along with the trucks had to be transported from dock to dock four times. The drilled VGS piles have a diameter of 508 mm and their lengths vary from 12 to 17 m. The piles have alternately been produced in a forward and backward slant position of 1:8.

Windmill park in Beersel canal area
Windmill park in Beersel canal area
Windmill park in Beersel canal area
Windmill park in Beersel canal area
Windmill park in Beersel canal area
Windmill park in Beersel canal area

Can we help you with your project?

We are happy to answer your questions! Would you like to know more about our projects, products and/or services? Please contact Paul Bochem

Paul Bochem

Share project:

Realization
29-06-2015 to 22-07-2015
Location
Beersel (B)
Client
H4A Windenergie
Contractor
Ecopower / Colruyt