A9 tunnel

We are working quite hard alongside the A9 freeway near Amsterdam Zuid-Oost. Under the authority of building company group IXAS and using 4 lanes simultaneously, we are working on the capacity for a huge tunnel with additional lanes and reversible lanes.

We are using four rigs in order to insert over 2,100 piles. We are processing four different pile diameters and lengths. The piles are being realized on-site so that we require fewer heavy transport actions to the site. The piles are being made by inserting a temporary framework (steel pipe) into the ground and placing concrete and a reinforcement basket into it. Subsequently, we pull the framework out to use it again.

A9 tunnel
A9 tunnel
A9 tunnel
A9 tunnel
A9 tunnel
A9 tunnel
A9 tunnel

Can we help you with your project?

We are happy to answer your questions! Would you like to know more about our projects, products and/or services? Please contact Rob Sman

Rob Sman

Share project:

Realization
18-02-2016 to 14-04-2016
Location
Amsterdam-Zuidoost
Client
Rijkswaterstaat
Contractor
Aannemerscombinatie IXAS
 
Fred Klaver
Project Manager