First Van der Valk hotel in Amsterdam

265 piles7 weeks

For the construction of the first Van der Valk hotel in Amsterdam, Vroom Foundation Technology is applying vibro combo piles. Designed by OeverZaaijer, the building will house 206 rooms, conference and wellness facilities and 135 parking lots.

We realize the capacity by applying almost 270 vibro combo piles. These are vibro piles with a prefab element in the cores. The prefab elements will be used to attach the floor of the parking basement to. The piles measure 26 m with a 559 mm diameter.

The hotel

The hotel will be built alongside the A2 and is accessible via the adjacent subway station and its own quay on Duivendrechtsevaart. On the third floor, a bar with wellness and fitness facilities plus a swimming pool will be built. This is also the point where the hotel rooms can be found until the upper layer of the high building.

First Van der Valk hotel in Amsterdam
First Van der Valk hotel in Amsterdam
First Van der Valk hotel in Amsterdam
First Van der Valk hotel in Amsterdam
First Van der Valk hotel in Amsterdam
First Van der Valk hotel in Amsterdam
First Van der Valk hotel in Amsterdam
First Van der Valk hotel in Amsterdam
First Van der Valk hotel in Amsterdam
First Van der Valk hotel in Amsterdam

Can we help you with your project?

We are happy to answer your questions! Would you like to know more about our projects, products and/or services? Please contact Rob Sman

Rob Sman

Share project:

Realization
25-05-2016 to 11-07-2016
Location
Amsterdam
Client
Van der Valk
Contractor
Pleijsier Bouw Genemuiden
Architect
OeverZaaijer Architectuur
 
Fred Klaver
Project Manager