Hyde Park development: 3800 apartments

3800 apartments and studio flats575 piles

Imposing new-build residential construction is emerging in Hoofddorp, at the junction of Kruisweg and Planetenweg. This site will accommodate 3800 apartments, studios and underground car parks.

This project forms part of the transformation of the former Beukenhorst-West office park into an urban residential neighbourhood called Hyde Park. The project is sustainable, has restricted access for traffic and has all mod cons. The wide boulevards, spacious courtyards and rooftop terraces make this into an alluring hyper-modern urban area.

Imposing pile lengths

We can be seen here making the foundations for blocks 7,8 & 9 with Vibro-combi piles. The relative ease with which vibro-piles can be positioned is combined with the ease of insertion of the prestressed pre-cast concrete section forming the core. The longest such sections measure 32.50 metres, which means that the tube digs 36 metres into the ground.

Click here for a 3D animation of the Vibro-combi pile process.

In order to reduce disruption from noise even more, we also use a noise-reducing jacket

Hyde Park development: 3800 apartments
Hyde Park development: 3800 apartments
Hyde Park development: 3800 apartments
Hyde Park development: 3800 apartments
Hyde Park development: 3800 apartments
Hyde Park development: 3800 apartments
Hyde Park development: 3800 apartments
Hyde Park development: 3800 apartments
Hyde Park development: 3800 apartments
Hyde Park development: 3800 apartments
Hyde Park development: 3800 apartments
Hyde Park development: 3800 apartments

Imposing pile lengths

We can be seen here making the foundations for blocks 7,8 & 9 with Vibro-combi piles. The relative ease with which vibro-piles can be positioned is combined with the ease of insertion of the prestressed pre-cast concrete section forming the core. The longest such sections measure 32.50 metres, which means that the tube digs 36 metres into the ground.

Click here for a 3D animation of the Vibro-combi pile process.

In order to reduce disruption from noise even more, we also use a noise-reducing jacket

Can we help you with your project?

We are happy to answer your questions! Would you like to know more about our projects, products and/or services? Please contact Rob Sman

Rob Sman

Share project:

Realization
01-12-2020 to 05-02-2021
Location
Hoofddorp
Client
Hyde Park Hoofddorp B.V.
Contractor
De Vries & Verburg Bouw B.V.
Architect
Barcode Architects
 
Fred Klaver
Project Manager

Can we help you with your project?

We are happy to answer your questions! Would you like to know more about our projects, products and/or services? Please contact Rob Sman

Rob Sman

Share project:

To top